M. ID 24-1344 Consider adoption of an ordinance of the City of Denton, a Texas home-rule municipal corporation, authorizing the approval of Change Order No. 5 to the Design-Build Agreement between the City of Denton and Beta Engineering, LLC, for the design and construction of the Hickory Gas Insulated Substation for Denton Municipal Electric; providing for the expenditure of funds therefor; and providing an effective date (RFQ 7670 - Change Order No. 5 in the not-to-exceed amount of $248,569.09, for a total contract award aggregated to $41,551,141.48). The Public Utilities Board recommends approval (6 - 0).